***** UPDATE INFORMATION ******
......We are working hard on flood protection system, of course focus on dike,
How big how high to protect flood in next rainy seasonss.
What we had done are ;
A) Award contract for topographical survey.
B) Award Contract Ground boring test.
C) Conceptual design of dikes.
D) Closely workout with expert, especially from JICA, last Friday Dec. 16, DR. Hiroshi Miki and big team from JICA visited Hi-Tech, glad to inform that Conceptual design of dikes are approved verbally.
E) Working on Loans amount of 350 – 400 Million Baht, not much progress on Government Soft Loan (same as all Industrial Estate / Parks) , but loan shall not be a problem to delay construction and completion of dikes.
Our tentative schedule ;
Mid Jan 2012 Completion of survey & soil test.
End Jan 2012 Completion of detail design.
Mid Feb 2012 Construction contract award.
End Sept 2012 Completion of dikes.
.....We are working against time, anyhow design shall be approved by
Authoritiesand JICA. Completion of dike by end of September 2012.
..... We hope to be able to finish in time, as we had done for Dewatering
and Rehab.
.....Tentative schedule for our next meeting will be around Jan 10 – 13, 2012.
.....Wishing all for A Merry X’Mas & A Happy New Year 2012.
.....Sincerely Yours,
.....Thavich Taychanavakul
.....Managing Director
.
|
|